Dust-free, rational working with combining our deaerated wall junction, floc-switch and exhaust-filter The deaerated wall junction is fixed into the drill hole (105mm diameter)
with an eccentric unit. Thus no particles of the insulating material are
discharged into the room air. The once fixed connection needs not to be
held during the filling process any more, so that you can already prepare
the next tray for the blowing-in. This system can be used time-saving on building sites and in the prefabrication
(e.g. of prefabricated building parts). |
||||
|
Side-view of the sample construction |
|
||
Easier working with our PE hose tracker for injection hoses With sloped trays the injection hoses must still be pushed in according
to the traditional method and be led by the construction worker. The sealing
of the injection drill hole was always difficult. |
||||
|
|
|||
|
||||